Why EnerGov reports leave gaps
Most permitting offices that run EnerGov have the same complaint: the data is in the system, but the reports people need every week are not. The director wants to know how many permits are waiting and for how long. Finance wants permit fee revenue to match the general ledger. The chief building official wants to see which inspectors are overloaded before inspections start slipping. The standard reports answer parts of these questions, usually as long lists rather than answers. This guide covers what EnerGov reporting looks like today, the five report gaps that come up most often, how to define each report so the numbers hold up, a worked fee reconciliation example with numbers, how to build the reports in SQL Server Reporting Services (SSRS) without changing the core system, and a checklist to run before any new report goes into production.
What EnerGov reporting means today
EnerGov is the older name for Tyler Technologies' Enterprise Permitting and Licensing product, and most staff still call it EnerGov. It holds permit cases, plan review cases, inspections, business and professional licenses, code enforcement cases, invoices and payments, and the workflow steps that move each case along. Residents and contractors reach it through Civic Access, the public portal where they search addresses or parcels, apply for permits, request inspections and pay invoices. Reporting comes in two layers. The first is the set of standard reports and searches inside the product, which are good for looking up one case or printing one document. The second is SQL Server Reporting Services, Microsoft's report server, where custom reports are designed with Report Builder and published for staff to run. For cities that Tyler hosts, Report Builder usually runs as a remote application against a Tyler hosted report server, so you design and publish reports there rather than on a local server. Either way, SSRS is where report gaps get closed, because it lets you write the query, the grouping and the layout yourself while the EnerGov application stays exactly as configured.
The five EnerGov report gaps that come up most
- Backlog aging: how many permits and plan reviews are open, grouped by how long they have been waiting (0 to 10 days, 11 to 30, 31 to 60, over 60), and at which workflow step they are stuck.
- Review turnaround: the number of days from a complete application to a decision, measured per review type, with the time the case sat waiting on the applicant shown separately from the time it sat with staff.
- Fee reconciliation: permit and license fees invoiced, paid, refunded and voided in EnerGov for a period, matched to the revenue posted in the general ledger, usually Tyler Munis.
- Inspector workload: inspections scheduled, completed and carried over per inspector per day, with travel area and inspection type, so supervisors can rebalance before requests stack up.
- Expirations and renewals: permits nearing expiration with no final inspection, and licenses due for renewal in the next 30, 60 and 90 days, so staff can notify holders before the deadline instead of after it.
Each of these is a question managers ask every week, and each needs a definition agreed in writing before anyone writes a query.
Backlog and turnaround: define the clock first
Backlog reports fail when nobody has decided when the clock starts and stops. Pick one start event, such as the date an application was marked complete rather than the date it was first submitted through Civic Access, because incomplete submissions inflate the numbers and punish staff for applicant delays. Pick one stop event, such as the date the permit was issued or the review was approved. Then decide how to treat time spent waiting on the applicant for corrections: most offices show it, but subtract it from staff turnaround. Group the open cases by workflow step as well as by age, because a backlog of 40 plan reviews tells you little, while knowing that 25 of them are waiting on one fire review step tells you where to send help. Run the report on the same day each week so the trend line means something, and keep last week's count beside this week's on the same page.
Fee reconciliation between EnerGov and Munis
Fee reconciliation is the gap finance feels most, because the auditor asks about it. EnerGov records an invoice when fees are assessed on a case and a payment when the applicant pays, whether at the counter or through Civic Access. The general ledger, in Munis or another ERP, records revenue when the payment batch is posted. Those are three different dates, and the totals rarely match on the first try. A useful reconciliation report lists, for one period, EnerGov payments by fee type and the general ledger revenue account each fee type maps to, then the Munis posted total for each of those accounts, then the difference. It shows refunds and voids as their own lines rather than netting them silently, and it flags any fee type with no mapped account. The point is not that the two systems should always agree to the penny on day one; it is that every difference has a named reason a finance director can repeat in a public meeting.
Worked example: one month of building permit fees
Take an invented but typical month. The EnerGov reconciliation report shows 612 building permit fee payments in October totaling $184,250. The Munis general ledger shows $181,900 posted to the building permit fee revenue account for October, a difference of $2,350. The report's detail lines explain it. First, a $1,500 permit fee was refunded on October 20 because the applicant withdrew the project. Munis posted the refund as a reduction of the revenue account, while the EnerGov payment total still counts the original payment and shows the refund on its own line. Second, an $850 payment taken through Civic Access late on October 31 went into a payment batch that posted on November 1, so it sits in November revenue in Munis. Subtract both from $184,250 and you get exactly $181,900, so the month reconciles. The actions are just as clear: show the EnerGov total net of refunds so it compares like with like, and agree a written cutoff rule with finance for payments taken on the last day of the month. Without the report, that $2,350 would have been an unexplained variance carried into the audit.
Inspector workload: what the report should show
- Inspections scheduled for each inspector today and for the next five working days, with inspection type and area of the city.
- Inspections completed yesterday per inspector, and those carried over to another day, with the reason when one was recorded.
- Average inspections per inspector per day over the last four weeks, so a heavy day stands out against a normal one.
- Reinspections as a share of all inspections by type, since a high reinspection rate on one trade points to a contractor education problem rather than a staffing problem.
- Requests made through Civic Access that are not yet assigned to an inspector, so nothing waits unseen in a queue.
Keep this report on one page. A supervisor should be able to read it at 7:30 in the morning and move inspections before inspectors leave the building.
How to build EnerGov reports in SSRS without customizing the core
The safe pattern is to treat SSRS as a reader of EnerGov data and never as a writer. Build and test every new report against your test or training environment first, then publish it to production. Use report parameters for the period, department and case type instead of hard coding them, so one report serves several teams. Put definitions that several reports share, such as which statuses count as open, in a shared dataset so every report uses the same rule. Add a footer to each report that states the definition, the data source and the time the report was run, because a printed report is often read long after it was created. Use SSRS subscriptions to send the weekly backlog and workload reports by email on a schedule, so managers get them without having to remember to run them. When a question needs data from both EnerGov and Munis, such as fee reconciliation, keep the matching logic in one report or one documented query rather than in a spreadsheet someone rebuilds by hand each month. If your city also uses GIS, check that EnerGov addresses and parcels match the Esri layers before you build any report grouped by area, because mismatched address keys quietly drop cases from map based totals. Tyler also offers API options for EnerGov; ask your Tyler contact what your contract includes before planning anything beyond reports.
Checklist before a new EnerGov report goes live
- The question the report answers is written in one sentence, and the person who asked for it has agreed to that sentence.
- Start and stop events, open statuses and date fields are defined in writing and stated in the report footer.
- The report was built and tested in the test or training environment, then compared with a manual count for at least one recent week or month.
- Totals tie to a known figure: case counts to an EnerGov search, fee totals to the Munis general ledger for the same period.
- Refunds, voids and cases waiting on the applicant appear as separate lines rather than being netted or hidden.
- Parameters cover period, department and case type, and the report runs in under a minute for a full year.
- Access is limited to the staff who need it, and any report that shows applicant contact details is treated as a public record request risk.
- An owner is named for the report, with a date to review it after the next fee schedule or workflow change.
Run this list for every new report and again after any EnerGov upgrade, since workflow and status changes can break a definition without breaking the report.
Frequently asked questions
- What reporting tool does EnerGov use for custom reports?
- Custom EnerGov reports are usually built in SQL Server Reporting Services (SSRS) with Microsoft Report Builder. For Tyler hosted cities, Report Builder typically runs as a remote application against a report server Tyler hosts.
- Is EnerGov the same as Tyler Enterprise Permitting and Licensing?
- Yes. Enterprise Permitting and Licensing is Tyler Technologies' current name for the product long known as EnerGov, and Civic Access is its public portal for applications, inspection requests and payments.
- Why do EnerGov permit fees not match the general ledger?
- EnerGov records invoices and payments on their own dates, while the general ledger records revenue when the payment batch posts. Refunds, voids, month end cutoff and fee types mapped to the wrong account explain most differences. A reconciliation report should show each one as a separate line.
- Can custom SSRS reports break EnerGov?
- Reports that only read data do not change how EnerGov works, which is why the safe pattern is read only reports built and tested in the test environment first. Upgrades can still change statuses or workflow steps, so review report definitions after each upgrade.
- Which EnerGov reports should a small permitting office build first?
- Backlog aging and fee reconciliation, because they answer the questions directors and auditors ask most. Inspector workload and expiration reports come next and reuse the same definitions.